Water treatment plant unit sizing for a growing town
Forecast demand for 30 years, choose a treatment process from raw water quality, size every unit from mixing to clear water storage, and cost a new plant.
Industry project · for Mopane Local Municipality, a municipality supplying 62,000 people from an ageing river-fed treatment works
Mopane Local Municipality supplies a town of about 62,000 people from a treatment works built in 1979 for 25,000. The works now runs above its capacity in summer, filters are backwashed by hand, and the town has had boil-water notices twice in two years after heavy rain made the river muddy. Several suburbs get water only on alternate days.
The municipality has funding for a feasibility design of a new works on the same site and wants it in eight weeks. You are the graduate engineer on the consultant's team, responsible for demand and unit sizing.
What you know: - population of 62,000 today, growing at about 2.4% a year; the design horizon is 30 years; - average domestic demand of about 150 litres per person per day, plus commercial and institutional demand of about 15% of domestic, and current non-revenue water of 32%, which the municipality wants to bring down to 20%; - raw water from a river weir, with turbidity between 15 NTU in winter and 400 NTU after summer storms, some colour, and occasional algae; - the plant must meet the national drinking water standard (SANS 241 in South Africa; IS 10500 if you adapt it for an Indian town); - 1.2 hectares of flat land beside the old works.
You will forecast demand, choose a conventional or alternative process, and size the units: rapid mixing, flocculation, clarification, rapid gravity filters, disinfection and clear water storage. You will draw a site layout and hydraulic profile and give a cost estimate.
Done means a feasibility design with a treatment capacity in Ml/day, each unit sized with its design criteria shown, a layout that fits the site, and a short report the municipality can use to apply for construction funding.
Demand workbook + process selection note + unit sizing workbook + hydraulic profile and site layout + cost estimate + feasibility report
Stack: Excel or Google Sheets, AutoCAD or LibreCAD, QGIS (site layout, optional), Python (optional)
- Demand and capacity20
Population, per capita demand, losses and peak factors combine into a defensible plant capacity in Ml/day.
- Process choice15
The process train is justified by raw water quality, including the 400 NTU storm case.
- Unit sizing35
Every unit is sized with its design criteria cited and checked, including redundancy for maintenance.
- Layout and hydraulics15
The layout fits 1.2 ha and the hydraulic profile flows by gravity with stated losses.
- Report and cost15
The report and cost estimate are clear enough to support a funding application.
Pass 60% · Merit 75% · Distinction 90%
Engineering Students
Diploma, B.Tech, B.E., BCA, MCA, or M.Tech students seeking practical experience.
Aspiring Developers
Developers who want to build proof-of-work capstone projects for tech resumes.
Job Seekers
Graduates looking for AI-evaluated code review & verified industry credentials.