Harmonics study for a data-centre UPS feed on utility and generator
Model the harmonic currents from a new data hall's UPS and cooling drives, scan for resonance, check compliance at the utility point of common coupling and on standby generators, and recommend mitigation with costs.
Industry project · for Blue Ridge Colo, a colocation data-centre operator adding a 2 MW data hall to its campus in Loudoun County, Virginia
Blue Ridge Colo is building Hall 4: 2 MW of IT load behind four 750 kVA double-conversion UPS modules, plus about 900 kW of cooling fans and pumps on VFDs. The hall is fed from the utility at 13.2 kV through a 3,000 kVA, 13.2 kV/480 V transformer with 5.75% impedance. The utility gives a fault level of 250 MVA at the point of common coupling. Two 2,000 kW diesel generators back up the hall, with a subtransient reactance of 0.15 per unit on their own rating.
Two things worry the operator: - The utility's interconnection agreement asks the site to meet IEEE 519 at the point of common coupling, and the utility engineer has asked for a harmonics study before energising. - At another campus, generators tripped on transfer and a UPS stayed on battery for 11 minutes because voltage distortion on generator power was too high for its input to accept.
The design team has two UPS options. One is a lower-cost unit with a 6-pulse rectifier and a passive input filter. The other is a unit with an active, IGBT front end that draws nearly sinusoidal current. They also want to know whether the 300 kvar power-factor capacitor bank planned for the mechanical board is a good idea.
You will build the system model, represent each load as a harmonic current source, run a frequency scan to find resonances, calculate voltage distortion and current distortion against the limits on both utility and generator supply, and compare mitigation options on cost. Everything is done in Python from first principles, and LTspice is optional for checking one case. No site data is needed beyond what is given here.
Done looks like a study report the utility engineer and the design team can both use: system data, source models, impedance scans, compliance tables for every operating case, a clear answer on the UPS choice and the capacitor bank, and a mitigation recommendation with cost.
Python models and scans + study report with system data, source models, compliance tables for utility and generator cases, mitigation comparison and recommendation
Stack: Python (numpy, matplotlib), LTspice (optional check), UPS and VFD datasheets, Markdown or Word
- Correct system model20
Source, transformer, generator and capacitor impedances are modelled across frequency on a common base, and the PCC and short-circuit ratio are stated.
- Credible source models20
Each UPS option and the VFDs are represented by harmonic spectra from datasheets or typical values, with phase-angle assumptions stated.
- Compliance answered25
Voltage THD and current TDD are calculated at the PCC and on the 480 V bus for utility and generator cases, and compared with the correct limits.
- Resonance and capacitor question15
Frequency scans show resonances with and without the 300 kvar bank, and the report gives a clear answer on whether to fit it.
- Costed recommendation20
At least three mitigation options are compared on effect and cost, and the recommendation covers both the UPS choice and the generator case.
Pass 60% · Merit 75% · Distinction 90%
Engineering Students
Diploma, B.Tech, B.E., BCA, MCA, or M.Tech students seeking practical experience.
Aspiring Developers
Developers who want to build proof-of-work capstone projects for tech resumes.
Job Seekers
Graduates looking for AI-evaluated code review & verified industry credentials.