Baseline schedule and earned-value control for a podium and car park package
Build a resource- and cost-loaded baseline schedule, then run month-9 earned-value analysis on a package that is slipping and propose a recovery plan with numbers.
Industry project · for Nahr Contracting, a Dubai contractor delivering the AED 186 million podium and car park package of a mixed-use tower
Nahr Contracting is delivering the podium and car park package of a 54-storey mixed-use tower in Dubai. The package is worth AED 186 million and covers three basement levels, a four-level podium, the car park ramps and the podium slab that the tower contractor needs to start above. The contract period is 22 months, with a delay penalty of AED 95,000 per day after the podium handover date.
The planning engineer who built the tender programme has left, and the programme was never cost-loaded. At month 9 the client's project manager is asking awkward questions: the site looks behind, the monthly valuation is lower than forecast, and the tower contractor is worried about its start date.
You will rebuild the baseline properly and then use it to tell the truth about month 9. Specifically: - a work breakdown structure for the package; - about 120 activities with durations based on quantities and productivity rates; - a CPM schedule in Primavera P6, MS Project or ProjectLibre, with the critical path to the podium handover; - resource and cost loading, and a planned S-curve; - an earned-value analysis at month 9 using the progress data in the brief: planned 38% complete, earned value at 31% of budget, and actual cost to date of AED 64.0 million; - a recovery plan with options, costs and the forecast handover date.
Done looks like a baseline a planner would accept, an honest month-9 report with CPI, SPI, a forecast cost at completion and a forecast handover date, and a recovery option the commercial manager can take to the client.
WBS + activity and logic workbook + baseline schedule file and PDF + cost-loaded S-curve + month-9 EVM workbook + recovery plan and progress report
Stack: Primavera P6, MS Project or ProjectLibre, Excel or Google Sheets, A charting tool such as Excel charts or Power BI
- Credible baseline30
The schedule is fully logic-linked, durations come from quantities and rates, and the critical path runs to the podium handover.
- Cost loading15
The cost-loaded schedule sums to AED 186 million and produces a sensible planned S-curve.
- Correct earned value25
PV, EV, AC, CPI, SPI, EAC and the forecast date are correct and interpreted in plain words.
- Recovery plan20
At least two recovery options are costed against the delay penalty and one is recommended with a date.
- Reporting10
The month-9 report would survive a client meeting: short, honest and backed by charts.
Pass 60% · Merit 75% · Distinction 90%
Engineering Students
Diploma, B.Tech, B.E., BCA, MCA, or M.Tech students seeking practical experience.
Aspiring Developers
Developers who want to build proof-of-work capstone projects for tech resumes.
Job Seekers
Graduates looking for AI-evaluated code review & verified industry credentials.